Kelana Jaya and Ampang LRT Extension



As far as we know, the RM7 billion LRT is expected to start by the end of this month. The paper works and all the documentation were prepared back in 2009-2010. However, as far as I know , the timeline for the completion is 2014.

The estimated total distance for the extension is 17km with 13 stations from Kelana Jaya until Putra Height.







Overall extension


    Proposed new LRT stations to be extended from Putra line (from Kelana Jaya):

    • STN 01 - Subang Depot near D’Aman Crimson Condos

    • STN 02 - Dana 1 Commercial Centre

    • STN 03 - Kelana Jaya Centre Point

    • STN 04 - Subang Parade (interchange to Subang Jaya KTM)

    • STN 05 - Summit USJ

    • STN 06 - SS 18

    • STN 07 - USJ 7

    • STN 08 - Taipan

    • STN 09 - USJ Digital Mall

    • STN 10 - USJ 21

    • STN 11 - Alam Megah 1

    • STN 12 - Alam Megah 2

    • STN 13 - Putra Heights Commercial Centre



    Proposed new LRT stations to be extended from Star line (from Bukit Jalil):

    • STN 01 - Awan Besar

    • STN 02 - PPR Kg. Muhibbah

    • STN 03 - Bukit Kinrara

    • STN 04 - Giant Kinrara

    • STN 05 - Kinrara Industrial Park

    • STN 06 - IOI Mall

    • STN 07 - Tesco

    • STN 08 - Rakan Muda

    • STN 09 - Tractor Malaysia

    • STN 10 - Puchong Perdana

    • STN 11 - Puchong Prima

    • STN 12 - Kampung Tengah

    • STN 13 - Putra Heights Commercial Centre

    Zulkifli Yusoff, Group Project Director said:

    About 15% of these works for the Kelana line extension and about 20% of the works for the Ampang Line extension have been completed

    Stations 5 to 9 (SS15 Subang Jaya to USJ14) are located at heavily built-up zones with not much space to build park-and-ride facilities.

    But there will be 1,400 parking bays at Station 4 (Subang Jaya KTM), 1,500 bays at Station 7 (USJ7), and 700 bays at Station 10 (USJ21), with Station 4 being integrated with Subang Jaya KTM Komuter Station.


    There will be adequate parking bays for park-and-ride. On top of that, we need effective bus feeder system to accommodate high demand in certain area. RapidKL will work out on the feeder bus system based on area density, demand pattern and efficient turning point.

    Let's hope that this project will complete in time. Surely, the price of properties around the alignment will increase :)

    Source: